2/24/23

Accomplished:

  • Met with Re Ops team to discuss research goals, methods, best practices, and potential participant compensation

  • Finished Interview questions/script

  • Finished survey question draft

  • Going through Red Hat’s preliminary research materials they sent us

  • Evaluating user forums to determine Red Hat’s presence

  • Received feedback on interview script and survey during sponsor standup meeting

  • Presented our project approach during class


Successes:

  • Finishing up interview script

  • Finishing up survey questions

  • Meeting with Re Ops team


Fails:

  • Our survey was too long; shortened this after feedback from our sponsor

  • Could not submit our research proposal on Friday (since we have not started any interviews)


Difficulties:

  • Finalizing survey and interview script

  • Moving past the research phase without interviewing participants


Goals of Next Week:

  • Conduct task Analysis for Red Hat’s existing documentation/learning materials

  • Send out survey on platforms

  • Interview recruiting

  • Submit research proposal


 
 

Recent Posts

See All
Progress Report #10

4/21/23 Accomplished: Two Round #2 Usability Study tests completed with experienced developers Round #2 Usability Study deliverables...

 
 
Progress Report #9

4/14/23 Accomplished: Round #1 Usability Study Summary of Round #1 testing Altering script for different rounds of testing Changed some...

 
 
Progress Report #8

4/07/23 Accomplished: Got feedback on wireframes/medium fidelity prototypes from Mary and Beau Medium fidelity prototypes User Feedback...

 
 
Tufts University ENP120 
Capstone Project
Spring 2023

Powered and secured by Wix

bottom of page