2/10/23

Accomplished:

  • Kickoff meeting with sponsor to learn more about the project

  • Presented preliminary project scope during class

  • Assigned project roles for everyone

  • Sent followup to sponsors

  • Scheduled weekly recurring meetings

Successes:

  • Held initial meeting with sponsors

  • Learned more about the project scope and goals

  • Sponsors answered our questions regarding the project

  • Team introductions + project introductions

Fails:

  • Were not able to meet with sponsor before class this Tuesday, thus our presentation left out some key details about the scope/goals of our project

Difficulties:

  • Scheduling initial kickoff meeting with our sponsors due to some members being out sick

Goals of Next Week:

  • Begin research on users, RedHat products, and RedHat competitors

  • Read through existing research given to us by sponsors

  • Reach out to sponsor to get list of contacts to conduct interviews

 
 

Recent Posts

See All
Progress Report #10

4/21/23 Accomplished: Two Round #2 Usability Study tests completed with experienced developers Round #2 Usability Study deliverables...

 
 
Progress Report #9

4/14/23 Accomplished: Round #1 Usability Study Summary of Round #1 testing Altering script for different rounds of testing Changed some...

 
 
Progress Report #8

4/07/23 Accomplished: Got feedback on wireframes/medium fidelity prototypes from Mary and Beau Medium fidelity prototypes User Feedback...

 
 
Tufts University ENP120 
Capstone Project
Spring 2023

Powered and secured by Wix

bottom of page